How to calculate concrete volume and formwork area.

By Natha Mohamed M.M., Founder of TapeLine · Updated 16 November 2026 · 2 min read

Concrete is measured in cubic metres. Formwork, the temporary mould, is measured in square metres of the concrete surface it touches. Both come straight from the drawing dimensions.

Formulas by member

MemberConcrete volumeFormwork area
Slablength × width × thicknessunderside (length × width) plus exposed edges (perimeter × thickness)
Beamwidth × depth below the slab × length (full depth if the slab is measured between beams)soffit (width × length) plus two sides ((depth − slab thickness) × length × 2)
Columnwidth × depth × heightperimeter × height
Strip footing or ground beamwidth × depth × lengthtwo sides (depth × length × 2)
Pile caplength × width × depthfour sides (perimeter × depth)
Bored pileπ × diameter² ÷ 4 × lengthnone when cast against the ground; allow for temporary casing or a permanent liner where specified

Worked example

Slab 6 m × 6 m × 0.20 m thick: volume 7.2 m³. Underside 36.0 m². Edges, if all four are exposed: 4 × 6 × 0.2 = 4.8 m².

Beam 0.30 m wide × 0.60 m deep × 6 m long, framing into a 0.20 m slab that is measured over the beam: concrete below the slab 0.3 × (0.6 − 0.2) × 6 = 0.72 m³. (The full 0.3 × 0.6 × 6 = 1.08 m³ applies only if the slab is measured between the beams.) Soffit 0.3 × 6 = 1.8 m². Two sides below the slab: 2 × (0.6 − 0.2) × 6 = 4.8 m². Formwork 6.6 m². Either way, the concrete where beam and slab overlap is counted once.

Column 0.30 m × 0.30 m × 3 m high: volume 0.27 m³. Formwork 4 × 0.3 × 3 = 3.6 m².

Where take-off mistakes happen

  • Double counting. Where a beam meets a slab, or a column meets a beam, measure the concrete once and deduct the overlap.
  • Wrong beam depth. Use the depth below the slab for side formwork, since the slab already forms the top.
  • Missing edges. Slab edges, upstands and parapets need their own formwork.
  • Mixed units. Convert millimetres to metres before multiplying.

From concrete to steel

Once volumes are known, the reinforcement tonnage follows from kilograms per cubic metre. See the rebar weight chart for bar weights and planning figures.

Guides by TapeLine, quantity take-off software from Natha & Co, founded by Natha Mohamed M.M.

Try Free Beta Version   See the 3D take-off

Locked in the beta

This feature is part of the full TapeLine experience.