Quantity take-off checklist for a building.

A consistent order stops items being missed or counted twice. This checklist follows the order a building is built, with the unit each item is measured in.

Take-off order and units

StageItemsUnits
SubstructureExcavation, piles, pile caps, ground beams, blinding, ground slabm³, number, m², m
FrameColumns, beams, suspended slabs, stairs, parapetm³, m²
FormworkAll concrete surfaces that need a mouldm²
ReinforcementBars by diameter, meshtonne, m²
WallsBlockwork, lintels, openings deductedm², number
OpeningsDoors, windows, glazingnumber, m²
FinishesPlaster, paint, tiles, ceilings, skirtingm², m
ExternalWaterproofing, paving, kerbs, drainagem², m
ServicesSockets, lights, fixtures, cable and pipe runsnumber, m

Habits that keep numbers right

  • Set the scale first on every page and check it against a known dimension.
  • Work level by level so each floor can be priced and checked on its own.
  • Mark off as you measure. A coloured overlay shows what is done and what is left.
  • Deduct openings once and use the same net area for plaster, paint and blocks.
  • Cross-check totals. Wall area divided by floor area, or steel kilograms per cubic metre of concrete, should look reasonable against past jobs.
  • Keep a note of assumptions such as slab thickness read from a section.

Finish with a bill

When the quantities are checked, they go into a bill of quantities where rates, overhead and profit turn them into a price.

Guides by TapeLine, quantity take-off software from Natha & Co, founded by Natha Mohamed M.M.

Try Free Beta Version   See the 3D take-off

Locked in the beta

This feature is part of the full TapeLine experience.